Two Days Before the Crane – The Heavy Prep Continues
This week’s video is live for you.
We’re officially two days out from crane day, and today is about getting everything staged properly. The Cummins engines are free, but we still need to deal with the mufflers, the day tanks, and build the gantry that will let us move the port engine once the starboard engine comes out.
Nothing flashy — just careful planning, fabrication, and making sure the sequence is right before the crane shows up.
Thank you for backing Operation Silent Running and following along in real time. Your support means more than you know.